Carbon Credits for India's Cement Industry: The FY2026-27 CCTS Squeeze

C² Team
Sep 17
4 min read

India's cement sector stopped being a voluntary carbon story on 8 October 2025. That is the date the Greenhouse Gases Emission Intensity Target Rules, 2025 were notified under the Environment (Protection) Act, 1986, handing 186 cement facilities legally binding emission intensity targets. The first compliance filing has already passed. The harder year is the one you are operating in right now.

Cement is an obligated sector, and 186 plants are already in it

The Rules cover four sectors in the first wave: aluminium (13 entities), cement (186), chlor-alkali (30) and pulp and paper (53) - 282 obligated entities in all. Refining, petrochemicals and textiles followed on 16 January 2026, taking the compliance mechanism to roughly 490 entities across seven sectors. Iron and steel and fertiliser targets are still pending.

Three design features matter for a cement plant:

  • Intensity, not absolute tonnes. Targets are set in tCO2e per tonne of product, so growth is not automatically penalised - but efficiency has to improve in step with output.

  • Gate to gate, Scope 1 plus Scope 2. Kiln fuel and process CO2 from calcination sit alongside purchased electricity. The system initially covers CO2 and perfluorocarbons.

  • Benchmarked targets. Plants with higher baseline intensity were given steeper cuts, so two plants inside the same group can carry very different obligations.

The baseline year is FY2023-24 for every covered entity. If you are also tracking steel exposure across the group, our note on carbon credits for cement and steel companies covers the cross-sector view.

Why FY2026-27 is the year that bites

The two-year trajectory is deliberately back-loaded. Roughly 40% of the required reduction falls in FY2025-26 and the remaining 60% in FY2026-27.

For cement specifically, most ordinary Portland cement and pozzolana Portland cement units carry two-year reduction targets in the 4.7% to 7.6% range. The Centre for Science and Environment's analysis puts the sector-wide average nearer 3.4% over two years - the least ambitious of the four first-wave sectors - partly because several entities carried no first-year target at all, owing to overlap with PAT Cycle VIII.

Read those two numbers together and the implication is uncomfortable. A plant that sailed through year one on a modest cut, or on no cut, now has to deliver the bulk of its reduction inside a single financial year, with compliance falling due on 31 July 2027. There is no second bite.

What a shortfall actually costs

If you miss your target, you buy and surrender Carbon Credit Certificates equal to the gap. If you fail to do that, the Central Pollution Control Board imposes environmental compensation at twice the average CCC price.

That formula is the whole point of the design: non-compliance is engineered to be the most expensive option on the table. The complication is that there is no settled market price yet. The CERC Regulations, 2026 confine CCC trading to CERC-registered power exchanges - IEX, PXIL and HPX - with no over-the-counter trading at the outset, and the Indian Carbon Market Portal only went live on 21 March 2026. Price discovery is still young.

How to size your exposure before the market prices it for you:

  1. Pull your verified FY2023-24 baseline intensity and your notified FY2026-27 target, and take the difference in tCO2e per tonne.

  2. Multiply that gap by projected FY2026-27 output. That is your CCC exposure in tonnes.

  3. Budget a price band, not a point estimate, and stress-test the top of it.

  4. Compare the result against the marginal abatement cost of your in-plant levers, tonne for tonne.

  5. Decide buy-versus-abate early. Procurement in July 2027 will not be cheap.

The levers that change the arithmetic

For most Indian cement plants, direct abatement is cheaper per tonne than buying certificates. That means credits should cover the residual gap, not the whole gap.

Clinker substitution is the first lever. India's clinker factor has historically run above the global average, so fly ash, granulated blast-furnace slag and calcined clay still leave headroom at many plants. Thermal substitution with refuse-derived fuel and biomass is the second. Waste heat recovery and renewable power purchase agreements attack the Scope 2 half of the intensity number.

NITI Aayog's Roadmap for Cement Sector Decarbonisation, released on 21 January 2026, frames the long arc: carbon intensity has to fall from about 0.63 tCO2e per tonne of cement to roughly 0.09-0.13 tCO2e by 2070, while production rises from 391 million tonnes in 2023 towards a projected 2.1 billion tonnes. The roadmap names refuse-derived fuels, clinker substitution, CCUS and effective CCTS implementation as the priorities.

Where the offset mechanism fits

Cement groups usually own assets that can generate credits rather than consume them. The CCTS offset mechanism lets non-obligated entities register projects - eight methodologies are approved, covering renewable energy, green hydrogen, industrial energy efficiency, landfill methane recovery, mangrove afforestation and more - with a project start date no earlier than 1 January 2025.

Captive renewables, waste heat recovery at non-obligated units, and afforestation on worked-out limestone quarries are all worth screening. Keep that stream separate in your accounts from voluntary market credits bought for net-zero claims: they are different instruments serving different audiences, and mixing them in one budget line is how procurement decisions go wrong.

Csquare works with Indian manufacturers on CCTS exposure modelling, credit procurement and offset project development. If you want your FY2026-27 gap sized before the market does it for you, talk to our team.

 
 
 